Donvale Residences Update
Donvale Residences is an exclusive collection of townhomes with intelligent floor-plans and highly considered designs by CS-A. It is currently under construction with anticipated completion in 2019.
December Update
– External plaster and final fix underway
– Internal painting commenced
– Mechanical carpark install completed
November Update
– Scaffolding is down!
-Driveway pour complete
-Kitchen and bathroom cabinetry install in progress
-General fixing commenced
October Update
-External render complete and painting commenced.
-Feature fluted glass windows and skylights in place.
-Balcony planter boxes complete.
-All scaffolding is expected to come down this month with internal fixing commencing shortly after.
September 2019
-Scaffolding is up on the driveway side.
-Brickwork is roughly halfway through and cladding will commence shortly.
-Plumbing and electrical rough in has commenced.
August 2019
-Framing and bracing complete.
-Steel structure complete.
-External windows and doors installed.
July 2019
-Top floor framing complete
-Roof trusses and windows being installed
-Drainage generally complete
-Next steps will be to lock up all residences
June 2019
-Ground and first-level framing and party walls complete
-Structural beams generally in place
-Drainage installation complete
May 2019
-Ground-level masonry complete
-Final slabs and external staircases complete
-Perimeter retaining walls and waterproofing complete
-Drainage installation commenced
April 2019
-Underground slabs complete
-Formwork and pouring of car stacker pit walls complete
-Ground level masonry commenced
-Drainage Plan approved