Donvale Residences Update

Donvale Residences is an exclusive collection of townhomes with intelligent floor-plans and highly considered designs by CS-A.  It is currently under construction with anticipated completion in 2019.

December Update

– External plaster and final fix underway

– Internal painting commenced

– Mechanical carpark install completed

November Update

– Scaffolding is down!

-Driveway pour complete

-Kitchen and bathroom cabinetry install in progress

-General fixing commenced

 

October Update 

-External render complete and painting commenced.

-Feature fluted glass windows and skylights in place.

-Balcony planter boxes complete.

-All scaffolding is expected to come down this month with internal fixing commencing shortly after.

September 2019

-Scaffolding is up on the driveway side.

-Brickwork is roughly halfway through and cladding will commence shortly.

-Plumbing and electrical rough in has commenced.

August 2019

-Framing and bracing complete.

-Steel structure complete.

-External windows and doors installed.

July 2019

-Top floor framing complete

-Roof trusses and windows being installed

-Drainage generally complete

-Next steps will be to lock up all residences

 

June 2019

-Ground and first-level framing and party walls complete

-Structural beams generally in place

-Drainage installation complete

May 2019

-Ground-level masonry complete

-Final slabs and external staircases complete

-Perimeter retaining walls and waterproofing complete

-Drainage installation commenced

Drainage going in.

April 2019

-Underground slabs complete

-Formwork and pouring of car stacker pit walls complete

-Ground level masonry commenced

-Drainage Plan approved

Underground slabs completed.